LTC3300-2
16
33002f
For more information www.linear.com/LTC3300-2
OPERATION
Cell Discharging (Synchronous)
When discharging is enabled for a given cell, the primary
side switch is turned on and current ramps in the primary
winding of the transformer until the programmed peak
current (I
PEAK_PRI
) is detected at the In P pin. The primary
side switch is then turned off, and the stored energy in
the transformer is transferred to the secondary-side cells
causing current to flow in the secondary winding of the
transformer. The secondary-side synchronous switch
is turned on to minimize power loss during the transfer
period until the secondary current drops to zero (detected
at In S). Once the secondary current reaches zero, the
secondary switch turns off and the primary-side switch is
turned back on thus repeating the cycle. In this manner,
charge is transferred from the cell being discharged to
all of the cells connected between the top and bottom of
the secondary side—thereby charging the adjacent cells.
In the example of Figure 2, the secondary-side connects
across 12 cells including the cell being discharged.
I
PEAK_PRI
is programmed using the following equation:
I
PEAK _PRI
=
R
SNS_PRI
Cell discharge current (primary side) and secondary-side
charge recovery current are determined to first order by
the following equations:
I
DISCHARGE
=
I
PEAK _PRI
2
S
S+ T
I
SECONDARY
=
I
PEAK _PRI
2
1
S+ T
η
DISCHARG
E
where S is the number of secondary-side cells, 1:T is the
transformer turns ratio from primary to secondary, and
η
DISCHARGE
is the transfer efficiency from primary cell
discharge to the secondary side stack.
Cell Charging
When charging is enabled for a given cell, the secondary-
side switch for the enabled cell is turned on and current flows
from the secondary-side cells through the transformer.
Once I
PEAK_SEC
is reached in the secondary side (detected
at the In S pin), the secondary switch is turned off and
current then flows in the primary side thus charging the
selected cell from the entire stack of secondary cells. As
with the discharging case, the primary-side synchronous
switch is turned on to minimize power loss during the cell
charging phase. Once the primary current drops to zero,
the primary switch is turned off and the secondary-side
switch is turned back on thus repeating the cycle.
I
PEAK_SEC
is programmed using the following equation:
I
PEAK _ SEC
=
50mV
R
SNS_SEC
Cell charge current and corresponding secondary-side
discharge current are determined to first order by the
following equations:
I
CHARGE
=
I
PEAK _ SEC
2
ST
S+ T
η
CHARGE
I
SECONDARY
=
I
PEAK _ SEC
2
T
S+ T
where S is the number of secondary cells in the stack, 1:T
is the transformer turns ratio from primary to secondary,
and η
CHARGE
is the transfer efficiency from secondary-side
stack discharge to the primary-side cell.
Each balancer’s charge transferfrequency” and duty
factor depend on a number of factors including I
PEAK_PRI
,
I
PEAK_SEC
, transformer winding inductances, turns ratio,
cell voltage and the number of secondary-side cells.
The frequency of switching seen at the gate driver outputs
is given by:
f
DISCHARGE
=
S
S+ T
V
CELL
L
PRI
I
PEAK _PRI
f
CHARGE
=
S
S+ T
V
CELL
L
PRI
I
PEAK _ SEC
T
where L
PRI
is the primary winding inductance.
Figure 3 shows a fully populated LTC3300-2 application
employing all six balancers.
LTC3300-2
17
33002f
For more information www.linear.com/LTC3300-2
OPERATION
Figure 3. LTC3300-2 6-Cell Active Balancer Module Showing Power Connections for the Multi-Transformer Application (CTRL = V
)
+
+
+
+
1:1
25mΩ
10µH
CELL 6
UP TO
CELL 12
CELL 5
CELL 2
CELL 1
10µH
C6
0.1µF
10µF
G6P
I6P
G6S
I6S
C5
G5P
I5P
G5S
I5S
C4
C3
LTC3300-2
C2
G2P
I2P
G2S
I2S
C1
G1P
I1P
G1SV
REG
BOOST
I1S
RTONSRTONP
BOOST
+
6.8Ω
BOOST
CTRL
V
25mΩ
1:1
25mΩ
10µH10µH
25mΩ
1:1
25mΩ
10µH10µH
25mΩ
1:1
25mΩ
10µH10µH
25mΩ
6.98k
33002 F03
22.6k10µF
10µF
10µF
10µF
SERIAL
COMMUNICATION
RELATED
PINS
A4
A3
A2
A1
A0
CSBI
SCKI
SDI
SDO
WDT
LTC3300-2
18
33002f
For more information www.linear.com/LTC3300-2
Balancing High Voltage Battery Stacks
Balancing series connected batteries which contain >>12
cells in series requires interleaving of the transformer sec-
ondary connections
in order to achieve full stack balancing
while limiting the breakdown voltage requirements of the
primary- and secondary-side power FETs. Figure 4 shows
typical interleaved transformer connections for a multicell
battery stack in the generic sense, and Figure 5 for the
specific case of an 18-cell stack. In these examples, the
secondary side of each transformer is connected to the
top of the cell that is 12 positions higher in the stack than
the bottom of the lowest voltage cell in each LTC3300-2
sub-stack. For the top most LTC3300-2 in the stack, it is
not possible to connect the secondary side of the trans-
former across 12 cells. Instead, it is connected to the top
of the stack, or effectively across only 6 cells. Interleaving
in this fashion allows charge to transfer between 6-cell
sub-stacks throughout the entire battery stack.
Max On-Time Volt-Sec Clamps
The LTC3300-2 contains programmable fault protection
clamps which limit the amount of time that current is
allowed to ramp in either the primary or secondary wind
-
ings in
the event of a shorted sense resistor. Maximum
on
time for all primary connections (active during cell
discharging) and all secondary connections (active during
cell charging) is individually programmable by connecting
resistors from the R
TONP
and R
TONS
pins to V
according
to the following equations:
t
ON(MAX)|PRIMARY
= 7.2µs
R
TONP
20kΩ
t
ON(MAX)|SECONDARY
= 1.2µs
R
TONS
15kΩ
For more information on selecting the appropriate
maximum on-times, refer to the Applications Information
section.
To defeat this function, short the appropriate R
TON
pin(s)
to V
REG
.
OPERATION
Figure 4. Diagram of Power Transfer Interleaving Through the
Stack, Transformer Connections for High Voltage Stacks
+
+
LTC3300-2
POWER STAGES
LTC3300-2
POWER STAGES
FROM CELL N-12
SECONDARY
TO CELL 24
PRI SEC
+
+
+
+
+
+
LTC3300-2
POWER STAGES
SEC PRI
SEC PRI
+
+
CELL 18
CELL 13
CELL 6
CELL 7
CELL 12
CELL N-6
CELL N
CELL 1
CELL 2
CELL 3
CELL 4
CELL 5
33002 F04
LTC3300-2
POWER STAGES
PRI
TOP
SEC
+
+

LTC3300IUK-2#TRPBF

Mfr. #:
Manufacturer:
Analog Devices / Linear Technology
Description:
Battery Management Addressable Hi Eff Bi-dir Multicell Bat
Lifecycle:
New from this manufacturer.
Delivery:
DHL FedEx Ups TNT EMS
Payment:
T/T Paypal Visa MoneyGram Western Union