LTC3300-1
16
33001fb
For more information www.linear.com/LTC3300-1
OPERATION
charge from the highest voltage cell(s) in the stack to other
lower voltage cells in the stack (active balancing). This
can be very efficient (in terms of charge recovery) for the
case where only a few cells in the overall stack are high,
but will be very inefficient (and time consuming) for the
case where only a few cells in the overall stack are low. A
bidirectional active balancing approach, such as employed
by the LTC3300-1, is needed to achieve minimum balanc
-
ing time and maximum charge recovery for all common
cell capacity errors.
V
CC
I
CHARGE
I
SECONDARY
I
PRIMARY
V
PRIMARY
V
SECONDARY
V
TOP_OF_STACK
L
PRI
10µH
G1P
I1P
R
SNS_SEC
25mΩ
R
SNS_PRI
25mΩ
G1S
I1S
I
LOAD
(48V)
(4V)
T: 1
5µs
Single-Cell Discharge Cycle for Cell 1 Single-Cell Charge Cycle for Cell 1
I
PEAK_PRI
= 2A
(I1P = 50mV)
t
I
PRIMARY
5µs
2A
t
–I
PRIMARY
~417ns
2A
t
–I
SECONDARY
52V
52.05V
t
V
PRIMARY
4V
50mV
50mV
50mV
48V
4V
48V
52V
t
V
SECONDARY
~417ns
I
PEAK_SEC
= 2A
(I1S = 50mV)
t
I
SECONDARY
33001 F02
52V
51.95V
t
V
PRIMARY
4V
50mV
4V
48V
50mV
50mV
52V
48V
t
V
SECONDARY
CELL 1
+
CELL 2
+
CELL 12
+
CELL 13
+
CELL N
+
Figure 2. Synchronous Flyback Balancing Example with T = 1, S = 12
Synchronous Flyback Balancer
The balancing architecture implemented by the LTC3300-1
is bidirectional synchronous flyback. Each LTC3300-1
contains six independent synchronous flyback controllers
that are capable of directly charging or discharging an
individual cell. Balance current is scalable with external
components. Each balancer operates independently of
the others and provides a means for bidirectional charge
transfer between an individual cell and a larger group of
adjacent cells. Refer to Figure 2.
LTC3300-1
17
33001fb
For more information www.linear.com/LTC3300-1
OPERATION
Cell Discharging (Synchronous)
When discharging is enabled for a given cell, the primary
side switch is turned on and current ramps in the primary
winding of the transformer until the programmed peak
current (I
PEAK_PRI
) is detected at the InP pin. The primary
side switch is then turned off, and the stored energy in
the transformer is transferred to the secondary-side cells
causing current to flow in the secondary winding of the
transformer. The secondary-side synchronous switch
is turned on to minimize power loss during the transfer
period until the secondary current drops to zero (detected
at In S). Once the secondary current reaches zero, the
secondary switch turns off and the primary-side switch
is turned back on thus repeating the cycle. In this manner,
charge is transferred from the cell being discharged to all
of the cells connected between the top and bottom of the
secondary side—thereby charging the adjacent cells. In the
example of Figure 2, the secondary-side connects across
12 cells including the cell being discharged.
I
PEAK_PRI
is programmed using the following equation:
I
PEAK _PRI
=
50mV
R
SNS_PRI
Cell discharge current (primary side) and secondary-side
charge recovery current are determined to first order by
the following equations:
I
DISCHARGE
=
I
PEAK _PRI
2
S
S+ T
I
SECONDARY
=
I
PEAK _PRI
2
1
S+ T
η
DISCHARG
E
where S is the number of secondary-side cells, 1:T is the
transformer turns ratio from primary to secondary, and
η
DISCHARGE
is the transfer efficiency from primary cell
discharge to the secondary side stack.
Cell Charging
When charging is enabled for a given cell, the secondary-
side switch for the enabled cell is turned on and current
flows from the secondary-side cells through the trans
-
former. Once I
PEAK_SEC
is reached in the secondary side
(detected at the In S pin), the secondary switch is turned
off and current then flows in the primary side thus charging
the selected cell from the entire stack of secondary cells. As
with the discharging case, the primary-side synchronous
switch is turned on to minimize power loss during the cell
charging phase. Once the primary current drops to zero,
the primary switch is turned off and the secondary-side
switch is turned back on thus repeating the cycle.
I
PEAK_SEC
is programmed using the following equation:
I
PEAK _SEC
=
50mV
R
SNS_SEC
Cell charge current and corresponding secondary-side
discharge current are determined to first order by the
following equations:
I
CHARGE
=
I
PEAK _SEC
2
ST
S+ T
η
CHARGE
I
SECONDARY
=
I
PEAK _SEC
2
T
S+ T
where S is the number of secondary cells in the stack, 1:T
is the transformer turns ratio from primary to secondary,
and η
CHARGE
is the transfer efficiency from secondary-side
stack discharge to the primary-side cell.
Each balancers charge transfer “frequency” and duty
factor depend on a number of factors including I
PEAK_PRI
,
I
PEAK_SEC
, transformer winding inductances, turns ratio,
cell voltage and the number of secondary-side cells.
The frequency of switching seen at the gate driver outputs
is given by:
f
DISCHARGE
=
S
S+ T
V
CELL
L
PRI
I
PEAK _PRI
f
CHARGE
=
S
S+ T
V
CELL
L
PRI
I
PEAK _SEC
T
where L
PRI
is the primary winding inductance.
Figure 3 shows a fully populated LTC3300-1 application
employing all six balancers.
LTC3300-1
18
33001fb
For more information www.linear.com/LTC3300-1
OPERATION
Figure 3. LTC3300-1 6-Cell Active Balancer Module Showing Power Connections for the Multi-Transformer Application (CTRL = V
)
+
+
+
+
1:1
25mΩ
10µH
CELL 6
UP TO
CELL 12
CELL 5
CELL 2
CELL 1
10µH
C6
0.1µF
10µF
G6P
CSBO
SCKO
SDOI
CSBI
SCKI
SDI
SDO
TOS
V
MODE
WDT
I6P
G6S
SERIAL
COMMUNICATION
RELATED
PINS
I6S
C5
G5P
I5P
G5S
I5S
C4
C3
LTC3300-1
C2
G2P
I2P
G2S
I2S
C1
G1P
I1P
G1SV
REG
BOOST
I1S
RTONSRTONP
BOOST
+
6.8Ω
BOOST
CTRL
V
25mΩ
1:1
25mΩ
10µH10µH
25mΩ
1:1
25mΩ
10µH10µH
25mΩ
1:1
25mΩ
10µH10µH
25mΩ
6.98k
33001 F03
22.6k10µF
10µF
10µF
10µF

LTC3300IUK-1#PBF

Mfr. #:
Manufacturer:
Analog Devices / Linear Technology
Description:
Battery Management Hi Eff Bi-dir Multicell Bat Balancer
Lifecycle:
New from this manufacturer.
Delivery:
DHL FedEx Ups TNT EMS
Payment:
T/T Paypal Visa MoneyGram Western Union